Well, we must confess it to you: nothing was done during the last 2 weeks ...
Nothing ...
The cause? Ho, small things to correct at the administrative level, paperwork ...
A document that I have not signed and returned after the issuance of the building permits (more than 3 month ago ...), a difference of 18 cm between the dimensions of the plan and the actual width of the house after construction, and the "police of contruction sites" has come to forbide further work on our house until all these are corrected !
Two weeks, the time to figure out which document did I failed to return (I'm French, I did not know !...), the time that our architect corrects the plans and submit it to the approval of the authority, and this Monday, workers were able to resume work.
Nothing really serious, "just" a few days lost.
Status of the situation: the house is supposed to be finished Oct. 31, which makes less than a month to finish all the remaining operations.
Possible or not?
Wolfgang and I met on the site this Saturday.
He is confident, he will put everything in its power to meet this tight deadlines!
We trust him!
Dear readers, we're certain you will follow with interest the next posts, to discover with us all the progresses until completion of our house.